Glendale Heights FenceGlendale Heights, IL fence estimates

Glendale Heights Fence Permits, Heights and Code Rules

This is the Glendale Heights fence code guide: when a permit is required, how tall a fence may be, and what you submit. A free estimate can cover the plat notes and the paperwork list. The fee is not printed on this page.

StreetHouseRear and side lines are the taller fence in this sketchFront of the house: low ornamental only
Illustration of a lot, a house, and fence lines. It is not a plat of survey and not the village’s drawing.

Is a permit required?

Section 11-4-8(B) says no permanent or temporary fence shall be erected, constructed, or installed without first having been issued a fence permit by the zoning administrator. The village brochure says permits must be obtained before construction.

The material pages point here for where the fence may stand: vinyl, wood, aluminum and iron, chain link, and pool fences. Repair points here because a new fence has to meet today’s section even when an old nonconforming fence may be repaired.

What to submit

The supplemental checklist, Rev 05/2020, asks for a completed application with the fence type, height, and color; a plat of survey showing the fence location; a signed Fence Permit Addendum; an HOA approval letter when one applies; contractor registration with the bond; and an owner-signed Easement Encroachment Agreement when the fence is on an easement.

The HOA page is the letter. It does not replace this permit. The applicant is the owner of record or the registered contractor doing the work, which is what the Building Permits page says. What to ask before you hire is on choosing a fence company.

How an application moves

These steps follow the checklist, the addendum, and the brochure in the current packet. They do not include a fee amount.

  • Mark the fence on a plat of survey that shows the lot lines. The village application asks for the location, the type, the height, and the color.
  • If a homeowners association covers the house, the village asks for that association’s approval letter with the permit. The letter does not replace the permit.
  • The applicant is the owner of record or the registered contractor doing the work. Include the signed Fence Permit Addendum. If the fence is on an easement, include the owner-signed Easement Encroachment Agreement.
  • The brochure in the current packet says to allow at least 10 working days. Phrase that as about two weeks, and confirm the timing with the village. Get approval before you buy materials.
  • Contact JULIE through illinois1call.com before any digging. This step does not print a phone number.
  • Posts go at least one-third of their length in the ground, in holes at least 24 inches deep, unless the approved plan is more specific. Follow that plan.
  • The addendum calls for a final inspection with 24 hours’ notice. Ask the village what the inspector will look at on your permit.

Heights

Height follows the yard and whether the fence is solid or open. “In front of the principal building” is set by how the building faces, not by the legal front-yard name. Note 2 on the table is the real front-of-building rule: no fence or wall except a hedge of 2.5 feet or less, or an ornamental fence of 3.5 feet or less. An ornamental fence is at least 70 percent open and is not chain link.

Open fences taller than 4 feet are treated as solid fences. The vision-clearance triangle is 2.5 feet for a solid fence and 3.5 feet for an open fence.

Maximum fence height in feet, Glendale Heights §11-4-8(D), districts other than industrial. Read the notes. The front-of-building row is note 2, not a 2-foot privacy fence.
LocationSolidOpen
Vision-clearance triangle2.5 feet3.5 feet
In front of the principal buildingHedge 2.5 feet, or no fenceOrnamental fence 3.5 feet
Front or corner side yard6 feet, note 34 feet, note 4
Interior side yard6 feet6 feet
Rear yard6 feet6 feet

Corner lots and through lots

Note 3: in the corner side yard, the fence may not extend more than 10 feet from the extension of the building line toward the lot line, except that a through lot may have a 6-foot fence. Note 4: open fences taller than 4 feet follow the solid-fence rules, and a through lot may have a 6-foot fence on the property line at the rear of the dwelling. The street-side case is written out on corner-lot fences.

The sketch above is an original illustration of a house and fence lines. It is not a plat and it is not the village’s drawing. The Planning and Zoning Commission and the Village Board have granted variations for corner side yards. This page does not name a property, a person, or a street.

Materials

Outside the industrial district, the permitted materials are chain link with no slats, in rear and interior side yards only; masonry or stucco; wood, and not plywood; wrought iron; and decorative PVC. No fence may be electrified or contain broken glass, barbed wire, or other material meant to injure, except the public-safety barbed-wire case the section itself states.

Aluminum and steel are not named. Confirm with the village that a product qualifies. The aluminum and iron page says the same thing. Industrial-district materials are a separate list in the same section. Confirm the zoning district before you use that list.

Colors

If the fence is painted or stained, the addendum limits it to white, black, gray, brown, or redwood, the same solid color on all sides. The checklist says neutral. Confirm a factory vinyl color, including tan or almond, with the village before you order. The vinyl page is that warning in longer form.

Posts, the finished face, and drainage

The addendum says posts are set at least one-third of their length in the ground, and post holes are at least 24 inches deep. Specifics on the approved plan control if they are stricter. The finished face goes out toward neighboring homes and streets. The unfinished face may go toward an alley.

Closed fences are at least 1 inch above grade so stormwater can pass, under §11-4-8(K). They may not block drainage. This guide uses 1 inch. It does not use older handouts that say 3 or 4 inches.

Hedges

The addendum says hedges and other closely spaced plants over 2 feet tall count as a fence and have to meet the fence rules. In front of the principal building, a hedge is limited to 2.5 feet. Section 11-4-8(A) already pulls hedges into the fence section.

Dog runs

The brochure describes dog runs as open fencing, no more than 8 feet tall, no more than 50 feet on a side, and at least 10 feet from lot lines. A dog run is still a fence. It does not create a front-yard chain-link permission. There is no separate dog-run URL in this launch.

Easements and utility locates

If the fence is on an easement, the checklist asks for an Easement Encroachment Agreement signed by the owner. Do not treat an easement as spare land for posts.

Contact JULIE before you dig. The public page is illinois1call.com. This guide does not print a dig number.

Lots next to a golf course

Section 11-4-8(G) allows protective netting on a lot that abuts a golf course: no more than 20 feet tall, installed no earlier than March 1 and removed no later than December 15, plastic or nylon, and not chain link or chicken wire. A permit is required. This page does not name the course.

Fences that do not meet today’s code

Section 11-4-8(I) says a fence that legally existed and does not conform may remain and be repaired. Section 11-4-8(H) requires maintenance in sound repair. A new fence meets this section. The repair page is the longer version of that split.

Review and the final inspection

The brochure in the current packet, revised February 28, 2019, says to allow at least 10 working days for review. Read that as about two weeks, and confirm the timing with the village. Get the approval before you buy materials.

The addendum calls for a final inspection with 24 hours’ notice. Ask what the inspector will check. The Building Permits page lists the adopted codes as the 2021 IRC, IBC, IEBC, and ISPSC, and the 2024 Illinois Energy Conservation Code.

Contractor registration bond

The contractor registration application lists a $20,000 surety bond, and Fence is one of the trades on that application. The bond is a contractor registration requirement. It is not a homeowner charge for the fence, and it is not printed here as a permit amount. The registration fee on that form is left off because the form used for this reading was undated.

Confirm the contractor’s registration with the village. This site does not look up registrations and does not claim one. The questions to put on a written estimate, including who files, are on choosing a fence company.

Where to confirm the permit fee

The village sets the fence permit fee and confirms the amount when the permit is approved. Check the village Building Permits page. No fee figure is printed on this site. The link is the Glendale Heights Building Permits page. A national cost article is not a substitute for that page.

The cost guide is Fixr and Angi, each with a date. It is not a fee schedule. Prices vary. A free estimate gives the real number. Use the contact form.

Nearby towns

Glendale Heights Fence takes free estimate requests in these places. Each one has its own section on the service area page. Name the place on the form.

FAQ

Do I need a permit to replace an existing fence?

The code requires a permit to erect, construct, or install a fence. Ask the village whether a like-for-like replacement is treated as a new installation. A new fence has to meet today’s rules. A legal nonconforming fence may remain and be repaired under §11-4-8(I).

How tall can a fence be on a corner lot?

The corner side yard may not carry the fence more than 10 feet past the extension of the building line, except a through lot, which may have a 6-foot fence on the rear property line. Rear and interior side yards are 6 feet. Confirm the yards on the plat.

Can I use chain link in my front yard?

No. Chain link with no slats is permitted in rear and interior side yards only. It is not an ornamental front-yard fence.

Can I add privacy slats to chain link?

No. The material line says chain link, no slats.

What colors can I paint or stain?

White, black, gray, brown, or redwood, the same solid color on all sides, if the fence is painted or stained. Confirm a factory color that is not on that list.

How deep do the post holes have to be?

The addendum says holes at least 24 inches deep, and posts set at least one-third of their length in the ground. Follow the approved plan if it asks for more.

How long does the permit take?

The brochure says to allow at least 10 working days. Read that as about two weeks, and confirm the timing with the village. Get approval before you buy materials.

How much is the permit?

The village sets the fence permit fee and confirms the amount when the permit is approved. The Building Permits page is the link. This site does not print a figure.